2009- Completion of gates
- Completion of the spur road
- Completion of well numbers 3, 4, 5 and 6
- Do the site work and pour the foundation for the Lodge and Fitness Center
- Build the first Outfitter’s Cabin
- Build the Trail and Wildlife Viewing Shelter at the pond
- Build one Ridge Casita for use by prospective land purchasers
- Partial installation of electric, cable and water lines
- Start construction of the Mountain Bike/Horseback Riding Trail System
- Clear parcels 26-37
- Seed and fertilize road slopes
- Purchase fish for stocking and continue Habitat and Wildlife Enhancement Program
- Purchase the following Home Owner’s Association equipment: pickup truck, skid steer blade, tractor
2010- Begin construction of the Lodge and Fitness Center
- Build the second Outfitter’s Cabin
- Build the second Trail and Wildlife Viewing Shelter
- Complete first phase of the Mountain Bike/Horseback Riding Trail System
- Continue installation of electric, cable and water lines
- Purchase fish for stocking and continue Habitat and Wildlife Enhancement Program
- Continue additional work on ranch roads, wells and water system
2011-
Complete construction of the Lodge and Fitness Center
-
Build the final Outfitter’s Cabin
-
Build the final Trail and Wildlife Viewing Shelter
-
Continue construction of the Mountain Bike/Horseback Riding Trail System
-
Continue installation of electric, cable and water lines
-
Compete Habitat and Wildlife Enhancement Program
-
Begin construction of the Equestrian Center
-
Continue additional work on ranch roads, wells and water system
- Begin Timber Management Program
2012- Complete the Equestrian Center
- Continue maintenance of Habitat and Wildlife Enhancement Programs
The above schedule may be modified at the discretion of Rare Earth New Mexico, LLC. The time schedule for completion of additional roads, electric/cable/water lines, wells and parcel openings will mirror the sale of current parcels.
|
|
|